博文

目前显示的是 二月, 2018的博文

Week 4

图片
The aim of week 4 The main task of this week is to connect the capacitors bank in series with the load components hence can be used to correct the power factor. The second objective is to test the programme complied in the ARM MCU of which the main functions was to detect the phase difference and to control the capacitors bank. Experiment procedures In the morning section, the main activity was to connect the capacitors bank in series with the load inductors. By converting the phase differences between the voltage and the current to the power factor, the required capacitance to correct the power factor can be calculated. Then the ARM MCU can give the active low signals to the certain branches of the capacitors which can then be enabled to compensate the power factor. Figure 1. Test of the relay module Trouble Shooting The first problem encountered in this week was that the measured power factor using the oscilloscope was much higher than the calculated power fa...

Week 3

图片
The aim of Week 3 The aim of this week is to complete the circuit design of the control circuit with MOSFET and test the code measurement. Achievements The voltage comparators (LM358N) were successfully applied to the whole circuit in this week. The phase difference between the voltage and current displayed on the oscilloscope is shown in the figure below.  Figure 1. Phase Difference between the Voltage and Current Hence, the next step of this project is to connect capacitors to the load in parallel so as to eliminate the inductive power factor. In other words, the phase difference between the current and voltage should be approximately zero. An updated circuit produced by software Proteus 7.8 can be observed in Figure 2. Figure 2: Updated Circuit with Capacitors and Switch Testing It can be seen that the circuit on the right hand side aimed to eliminate the inductive power factor with capacitors connected in parallel. In addition, the circuit on the left ha...

Week 2

图片
The aim of Week 2 In this week, we need to find out how to use zero crossing detector and design a circuit to measure the   phase difference between voltage and current on the transmission line. We decided to simulate the circuit on Proteus first and then build the actual circuit on the board. Time arrangement   Feb. 5th-Feb. 6th: Try to apply a zero crossing detector (AQ-H) to find out the zero points of voltage and current on the transmission line. However, after several experiments, we found out that this item could not achieve the function as expected, so we started to look for other methods of measurement. Feb.7th: Group discussion and find a possible method of phase difference measurement by using to voltage comparator. Feb.8th: Use software Proteus to design and simulate an appropriate circuit and arrange a group meeting with our academic advisor. Feb.9th: Try to add some electrical components to the basic detector circuit to avoid unexpected inte...

Week 1

图片
The aim of Week 1 In the first week, the basic circuit model and theoretic information were determined. Several tests were conducted which indicated that the method to realize power factor correction needed to reconsidered and  improved.  Background theory Power factor is defined as the ratio of real power to the apparent power which is utilized to measure the efficiency of the power system. An triangle could be used to demonstrate the relationship between these parameters in the figure 1.  Figure 1. Triangle relationship of Power The value of power factor will tend to 1 if the efficiency of the system is high enough. Therefore, in order to improve the operating efficiency, the reactive power ought to be reduced to minimize the theta in the triangle.  Testing and Results The most straightest way to increase PF is to add capacitors to reduce Q. In this project, capacitor banks controlled by BJT were utilized to compensate the negative rea...